WECL-PT-01

Exchange of Information for Congestion Management – Short Term

1. Description of the Use Case

1.1. Name of the Use Case

IDArea /Domain(s)/Zone(s)Name of the Use Case
1None,WECL-PT-01

1.2. Version Management

Version No.DateName of author(s)ChangesApproval status
None2021-07-05T00:00:00E-REDES
NESTER
REN
INESC TEC,NoneNone

1.3. Scope and Objectives of Use Case

ScopeThis BUC is focused on describing in detail each process phase of the ASM report, stating what information should be exchanged and what rules should be established between DSO and TSO in order to procure congestion management products for short-term (intraday, day-ahead).
Objective(s)1- Design and detail each process phase of ASM report so that it can serve as a basis for future developments.
2- Coordination of the use of flexibility for different voltage levels.
3- Identify what information should be shared between DSO and TSO for each of the flexibility procurement process phases for short terms congestion management, namely for the technical selection and validation of the bids by the relevant system operator.
4- Develop information exchange mechanisms to enable market-based procurement of flexibility products.
Related business case(s)WECL-PT-02, WECL-PT-03, SUC-01, SUC-02, SUC-03, SUC-04, SUC-05

1.4. Narrative of Use Case

Short description

Flexible resources connected to transmission and distribution system can provide flexibility to system operators to eliminate congestions through a market mechanism. This BUC in transmission and/or distribution system, in order to keep power flows within the accepted thermal limits of the lines. These information exchanges of information mechanisms should be adaptable to any future market model or governance issues. Some different time frame markets will be examined: • Day Ahead • Intraday For each time frame, we will approach some of the following process phases of ASM report:

  • Prepare/Pre-qualification: The process in which it is checked whether a unit can deliver the product it intends to sell, taking into account the network conditions.
  • Plan/Forecast: Planning of grid utilization and identifying potential congestions.
  • Market Phase: Bids collection and selection, short-term contracts (capacity products) and short-term products/services (selection of energy products)
  • Monitoring and Activation: Grid monitoring and flexibility bids activation to solve the forecasted congestion management
  • Measurement and Settlement phase: Validation of delivery Some of the above process phases may be similar for both time frames. In this Business Use Case, the measurement and settlement phase will not be addressed. The developed information exchange mechanisms will be implemented in order to have a verification process.

Complete description

Flexible resources connected to transmission and distribution system can provide flexibility to system operators to eliminate congestions through a market mechanism. This BUC describes the exchanges of information and the processes that should be established for different scenarios: pre-qualification, plan/forecast, market phase and monitoring and activation phase. For each scenario, we will always take into account different timeframes (intraday and day-ahead) and how they are related. Pre-qualification The pre-qualification process should start after a flexibility service provider expresses interest in entering the flexibility market. This process serves to ensure that a particular flexibility service provider is capable of delivering a given product. In order to do that, two types of pre-qualification should be considered: Product Pre-qualification and Grid Pre-qualification. The former ensures that the resource contains the technical requirements to be able to deliver the product and proceed to the market phase and eventually selected by a system operator. These technical requirements are defined by DSO and TSO and after the FSP indicates the attributes of the product it wants to deliver, a pre-qualification test should be performed to verify that all attributes are in compliance with the technical requirements. This test may be repeated on a periodic basis or whenever the characteristics of the product are found to change significantly. The product pre-qualification can be done either by the DSO or TSO, regardless of its location. In case a system operator wants to activate a product already pre-qualified by another system operator, the former should have access to this information in order to make the process more efficient and not to pre-qualify the same product twice. Regarding grid pre-qualification, this process ensures that the product provided by the Flexible Service Provider will not cause constraints in the networks where it is connected. This process can be avoided if the System Operators have already identified the areas where flexibility is always allowed. The grid pre-qualification should be performed by the System Operator of the network to which the product is connected in order to verify if the maximum capacity of the product does not impact the network it is connected to. If the results of the two types of pre-qualification are approved, the entry of the FSP into the flexibility market is allowed. The Pre-qualification scenario is independent of the time-frame, since it is a process that happens before the market phase. Plan/Forecast In this phase the System Operators take into account the utilization of their grid. Based on forecasts the Systems Operators checks the power flows to detect whether or not there will be possible congestion in the network. In case the grid capacity is insufficient to meet the forecasted electricity production or consumption, System Operators may resort to the flexibility market to resolve this type of issue. This phase is done for two different timeframes, day-ahead and intraday. On the one hand, the day-ahead forecasts are made for D-1. On the other hand, the intraday forecasts are made every 4 hours in order to improve the accuracy of the predicted flow of electricity that were made for the day-ahead. The objectives of this phase are to identify possible congestions in the network and to support the procurement in the flexibility markets. Market Phase The market phase starts after the system operators forecast network congestion. In this phase, the system operators are focused on collecting and selecting bids from FSPs. These bids can be in the day-ahead market, which occurs on D-1, in the intraday market, which occurs already inside D every 4 hours, or they can come from the long-term market (BUC-2). The intraday market is a complement to the day-ahead market. The possible failures or unforeseen events that were not covered in the day-ahead should be corrected in the intraday market. In the bid selection process, the SO should pay attention to whether the bid is located in its own network, or in another network. In the latter case, the SO should consult the SO where the bid is located so it can evaluate the constraints that may arise if the bid is accepted and activated. After this phase, the need arises to sort the accepted bids by a merit order list. This Business Use Case will address a multi-level market model. Monitoring and Activation This phase occurs after the list of bids sorted by a merit order is defined. The SO selects the bid it wants to activate, if the bid is located in the network of another SO, the latter should be consulted to validate the activation of this bid. If the SO’s need is not resolved this process is repeated iteratively until the SO needs are solved.

1.5. Key Performance Indicatiors (KPI)

IDNameDescriptionReference to mentioned use case objectives

1.6. Use case conditions

Assumptions
WECL-PT-01
Prerequisites
WECL-PT-01

1.7. Further information to the use case for classification/mapping

Relation to other use cases
Level of depth
Prioritisation
Generic, regional or national relation
Generic
Nature of the use cases
Business Use Case
Further keywords for classification
Congestion management, DSO-TSO Coordination, DSO-TSO Exchange of Information

1.8. General remarks

General remarks

2. Diagrams of Use Case

BUC-1 Diagram Prequalifiaction_1_SequenceDiagram Plan_Forecast_ST MarketPhase_ST Activation

3. Technical Details

3.1. Actors

Actor NameActor TypeActor DescriptionFurther information specific to this Use Case
DSORoleAccording to the EDSO, the DSOs are “the operating managers (and sometimes owners) of energy distribution networks, operating at low, medium and, in some member states, high voltage levels (LV, MV)”.
TSORoleAccording to the European Commission, the TSO is “an organisation committed to transporting energy in the form of natural gas or electrical power on a national or regional level, using fixed infrastructure”. The certification procedure for TSOs is listed in Article 10 of the 2009 Electricity and Gas Directives.
MO DSORoleAccording to Article 2(7) of the Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast), market operator designates “an entity that provides a service whereby the offers to sell electricity are matched with bids to buy electricity”.
MO TSORoleAccording to Article 2(7) of the Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast), market operator designates “an entity that provides a service whereby the offers to sell electricity are matched with bids to buy electricity”.
FSPRoleDefined as any legal entity that offers flexibility services in the market.

3.2. References

No.References TypeReferenceStatusImpact on Use CaseOrganistaor / OrganisationLink

4. Step by Step Analysis of Use Case

4.1. Overview of Scenarios

No.Scenario NameScenario DescriptionPrimary ActorTriggering EventPre-ConditionPost-Condition
NonePrepare/PrequalificationThe process in which it is checked whether a unit can deliver the product it intends to sell, taking into account the network conditionsPrepare/Prequalification
NonePlan/ForecastPlanning of grid utilization and identifying potential congestions.Plan/Forecast
NoneMarket PhaseBids collection and selection, short-term contracts (capacity products) and short-term products/services (selection of energy products).Market Phase
NoneMonitoring & ActivationGrid monitoring and flexibility bids activation to solve the forecasted congestion management.Monitoring & Activation

Notes

4.2. Steps – Scenarios

Scenario Name:
Prepare/Prequalification
Step No.Event.Name of Process/ ActivityDescription of Process/ Activity.ServiceInformation Producer (Actor)Information Receiver (Actor)Information ExchangedRequirements, R-ID
1.1FSP requests to be pre-qualifiedDefine the prequalification requirementsNoneNone
1.2NoneSend the prequalification requirementsNoneNoneDSOMO DSOInfo1
1.3NoneSend the prequalification requirementsNoneNoneTSOMO TSOInfo1
1.4NoneNotifies that he is interested in providing flexibility services.FOR DSONoneFSPMO DSO
1.5NoneSend the prequalification requirementsFOR DSONoneMO DSOFSPInfo1
1.6NoneForward the fulfilled prequalification requirementsFOR DSONoneFSPMO DSO
1.7NoneForward the fulfilled prequalification requirementsFOR DSONoneMO DSODSOInfo1
1.8NoneEvaluation of the Product & Grid prequalification requirementsFOR DSONoneDSODSO
1.9NoneRequest additional prequalification informationFOR DSONoneDSOMO DSO
1.1NoneRequest additional prequalification informationFOR DSONoneMO DSOFSP
1.11NoneSend additional prequalification informationFOR DSONoneFSPMO DSO
1.12NoneSend additional prequalification informationFOR DSONoneMO DSODSO
1.13NoneAccept / Reject registration on MarketFOR DSONoneDSOMO DSOInfo3
1.14NoneNotify of prequalification resultFOR DSONoneMO DSOFSP
1.15NoneNotifies that he is interested in providing flexibility services.FOR TSONoneFSPMO TSO
1.16NoneSend the prequalification requirementsFOR TSONoneMO TSOFSPInfo1
1.17NoneForward the fulfilled prequalification requirementsFOR TSONoneFSPMO TSO
1.18NoneChecks the Location of the FSPFOR TSONoneMO TSOMO TSO
1.19NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSOInfo1
1.2NoneEvaluation of the Product & Grid prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneTSOTSO
1.21NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSO
1.22NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.23NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneFSPMO TSO
1.24NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSO
1.25NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSOInfo5
1.26NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.28NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSOInfo1
1.29NoneEvaluation of the Product prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOTSO
1.3NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSO
1.31NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.32NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.33NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSO
1.34NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSOInfo5
1.35NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSOInfo4
1.36NoneEvaluation of the Grid prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSODSO
1.37NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSO
1.38NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.39NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.4NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSO
1.41NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSOInfo7
1.42NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
2.1NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOTSO
2.3NoneExchange information about possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneInfo8
2.4NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.5NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.6NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.7NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.8NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.9NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.1NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.11NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
2.12NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.13NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.14NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.15NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.16NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.17NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.18NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.19NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.21NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
3.1NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO DSO
3.2NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO TSO
3.3NoneInforms the amount of flexibility requiredNoneNoneDSOMO DSOInfo11
3.4NoneInforms the amount of flexibility requiredNoneNoneTSOMO TSOInfo11
3.5NoneBids SelectionNoneNone
3.6NoneSelects the bids that may be a solutionFor DSONoneMO DSOMO DSO
3.7NoneSend the bidsFor DSONoneMO DSODSOInfo14
3.8NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For DSONoneDSODSO
3.9NoneSend the accepted/rejected bidsFor DSONoneDSOMO DSOInfo14
3.1NoneNotifies the resultFor DSONoneMO DSOFSP
3.11NoneSelects the bids that may be a solutionFor TSONoneMO TSOMO TSO
3.12NoneSend the bidsFor TSONoneMO TSOTSOInfo16
3.13NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For TSONoneTSOTSO
3.14NoneSend the accepted/rejected bidsFor TSONoneTSOMO TSOInfo16
3.15NoneCheck the Location of the bidsFor TSONoneMO TSOMO TSO
3.16NoneNotifies the resultFor TSO If the bid is connected to the Transmission GridNoneMO TSOFSP
3.17NoneSend the information of the bidFor TSO If the bid is connected to the Distribution GridNoneMO TSODSOInfo18
3.18NoneEvaluates grid constraintsFor TSO If the bid is connected to the Distribution GridNoneDSODSO
3.19NoneAccept/Reject bidFor TSO If the bid is connected to the Distribution GridNoneDSOMO TSOInfo19
3.2NoneNotifies the resultFor TSO If the bid is connected to the Distribution GridNoneMO TSOFSP
4.1NoneSharing of accepted bidsNoneNoneInfo20
4.2NoneChecks grid constrainsFor bids located in Distribution GridNoneDSODSO
4.3NoneInforms what Bids can/cannot be activatedFor bids located in Distribution GridNoneDSOTSOInfo20
4.4NoneChecks grid constrainsFor bids located in Transmission GridNoneTSOTSO
4.5NoneInforms what Bids can/cannot be activatedFor bids located in Transmission GridNoneTSODSOInfo20
4.6NoneAllows/Not allow bid activationNoneNoneDSOMO DSOInfo23
4.7NoneAllows/Not allow bid activationNoneNoneTSOMO TSOInfo24
4.8NoneInforms the resultNoneNoneMO DSOFSP
4.9NoneInforms the resultNoneNoneMO TSOFSP
4.1NoneInforms the activation of the bidNoneNoneFSPMO DSO
4.11NoneInforms the activation of the bidNoneNoneFSPMO TSO
Scenario Name:
Plan/Forecast
Step No.Event.Name of Process/ ActivityDescription of Process/ Activity.ServiceInformation Producer (Actor)Information Receiver (Actor)Information ExchangedRequirements, R-ID
1.1FSP requests to be pre-qualifiedDefine the prequalification requirementsNoneNone
1.2NoneSend the prequalification requirementsNoneNoneDSOMO DSOInfo1
1.3NoneSend the prequalification requirementsNoneNoneTSOMO TSOInfo1
1.4NoneNotifies that he is interested in providing flexibility services.FOR DSONoneFSPMO DSO
1.5NoneSend the prequalification requirementsFOR DSONoneMO DSOFSPInfo1
1.6NoneForward the fulfilled prequalification requirementsFOR DSONoneFSPMO DSO
1.7NoneForward the fulfilled prequalification requirementsFOR DSONoneMO DSODSOInfo1
1.8NoneEvaluation of the Product & Grid prequalification requirementsFOR DSONoneDSODSO
1.9NoneRequest additional prequalification informationFOR DSONoneDSOMO DSO
1.1NoneRequest additional prequalification informationFOR DSONoneMO DSOFSP
1.11NoneSend additional prequalification informationFOR DSONoneFSPMO DSO
1.12NoneSend additional prequalification informationFOR DSONoneMO DSODSO
1.13NoneAccept / Reject registration on MarketFOR DSONoneDSOMO DSOInfo3
1.14NoneNotify of prequalification resultFOR DSONoneMO DSOFSP
1.15NoneNotifies that he is interested in providing flexibility services.FOR TSONoneFSPMO TSO
1.16NoneSend the prequalification requirementsFOR TSONoneMO TSOFSPInfo1
1.17NoneForward the fulfilled prequalification requirementsFOR TSONoneFSPMO TSO
1.18NoneChecks the Location of the FSPFOR TSONoneMO TSOMO TSO
1.19NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSOInfo1
1.2NoneEvaluation of the Product & Grid prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneTSOTSO
1.21NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSO
1.22NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.23NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneFSPMO TSO
1.24NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSO
1.25NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSOInfo5
1.26NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.28NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSOInfo1
1.29NoneEvaluation of the Product prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOTSO
1.3NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSO
1.31NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.32NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.33NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSO
1.34NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSOInfo5
1.35NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSOInfo4
1.36NoneEvaluation of the Grid prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSODSO
1.37NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSO
1.38NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.39NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.4NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSO
1.41NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSOInfo7
1.42NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
2.1NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOTSO
2.3NoneExchange information about possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneInfo8
2.4NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.5NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.6NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.7NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.8NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.9NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.1NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.11NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
2.12NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.13NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.14NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.15NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.16NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.17NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.18NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.19NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.21NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
3.1NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO DSO
3.2NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO TSO
3.3NoneInforms the amount of flexibility requiredNoneNoneDSOMO DSOInfo11
3.4NoneInforms the amount of flexibility requiredNoneNoneTSOMO TSOInfo11
3.5NoneBids SelectionNoneNone
3.6NoneSelects the bids that may be a solutionFor DSONoneMO DSOMO DSO
3.7NoneSend the bidsFor DSONoneMO DSODSOInfo14
3.8NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For DSONoneDSODSO
3.9NoneSend the accepted/rejected bidsFor DSONoneDSOMO DSOInfo14
3.1NoneNotifies the resultFor DSONoneMO DSOFSP
3.11NoneSelects the bids that may be a solutionFor TSONoneMO TSOMO TSO
3.12NoneSend the bidsFor TSONoneMO TSOTSOInfo16
3.13NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For TSONoneTSOTSO
3.14NoneSend the accepted/rejected bidsFor TSONoneTSOMO TSOInfo16
3.15NoneCheck the Location of the bidsFor TSONoneMO TSOMO TSO
3.16NoneNotifies the resultFor TSO If the bid is connected to the Transmission GridNoneMO TSOFSP
3.17NoneSend the information of the bidFor TSO If the bid is connected to the Distribution GridNoneMO TSODSOInfo18
3.18NoneEvaluates grid constraintsFor TSO If the bid is connected to the Distribution GridNoneDSODSO
3.19NoneAccept/Reject bidFor TSO If the bid is connected to the Distribution GridNoneDSOMO TSOInfo19
3.2NoneNotifies the resultFor TSO If the bid is connected to the Distribution GridNoneMO TSOFSP
4.1NoneSharing of accepted bidsNoneNoneInfo20
4.2NoneChecks grid constrainsFor bids located in Distribution GridNoneDSODSO
4.3NoneInforms what Bids can/cannot be activatedFor bids located in Distribution GridNoneDSOTSOInfo20
4.4NoneChecks grid constrainsFor bids located in Transmission GridNoneTSOTSO
4.5NoneInforms what Bids can/cannot be activatedFor bids located in Transmission GridNoneTSODSOInfo20
4.6NoneAllows/Not allow bid activationNoneNoneDSOMO DSOInfo23
4.7NoneAllows/Not allow bid activationNoneNoneTSOMO TSOInfo24
4.8NoneInforms the resultNoneNoneMO DSOFSP
4.9NoneInforms the resultNoneNoneMO TSOFSP
4.1NoneInforms the activation of the bidNoneNoneFSPMO DSO
4.11NoneInforms the activation of the bidNoneNoneFSPMO TSO
Scenario Name:
Market Phase
Step No.Event.Name of Process/ ActivityDescription of Process/ Activity.ServiceInformation Producer (Actor)Information Receiver (Actor)Information ExchangedRequirements, R-ID
1.1FSP requests to be pre-qualifiedDefine the prequalification requirementsNoneNone
1.2NoneSend the prequalification requirementsNoneNoneDSOMO DSOInfo1
1.3NoneSend the prequalification requirementsNoneNoneTSOMO TSOInfo1
1.4NoneNotifies that he is interested in providing flexibility services.FOR DSONoneFSPMO DSO
1.5NoneSend the prequalification requirementsFOR DSONoneMO DSOFSPInfo1
1.6NoneForward the fulfilled prequalification requirementsFOR DSONoneFSPMO DSO
1.7NoneForward the fulfilled prequalification requirementsFOR DSONoneMO DSODSOInfo1
1.8NoneEvaluation of the Product & Grid prequalification requirementsFOR DSONoneDSODSO
1.9NoneRequest additional prequalification informationFOR DSONoneDSOMO DSO
1.1NoneRequest additional prequalification informationFOR DSONoneMO DSOFSP
1.11NoneSend additional prequalification informationFOR DSONoneFSPMO DSO
1.12NoneSend additional prequalification informationFOR DSONoneMO DSODSO
1.13NoneAccept / Reject registration on MarketFOR DSONoneDSOMO DSOInfo3
1.14NoneNotify of prequalification resultFOR DSONoneMO DSOFSP
1.15NoneNotifies that he is interested in providing flexibility services.FOR TSONoneFSPMO TSO
1.16NoneSend the prequalification requirementsFOR TSONoneMO TSOFSPInfo1
1.17NoneForward the fulfilled prequalification requirementsFOR TSONoneFSPMO TSO
1.18NoneChecks the Location of the FSPFOR TSONoneMO TSOMO TSO
1.19NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSOInfo1
1.2NoneEvaluation of the Product & Grid prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneTSOTSO
1.21NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSO
1.22NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.23NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneFSPMO TSO
1.24NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSO
1.25NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSOInfo5
1.26NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.28NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSOInfo1
1.29NoneEvaluation of the Product prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOTSO
1.3NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSO
1.31NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.32NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.33NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSO
1.34NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSOInfo5
1.35NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSOInfo4
1.36NoneEvaluation of the Grid prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSODSO
1.37NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSO
1.38NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.39NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.4NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSO
1.41NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSOInfo7
1.42NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
2.1NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOTSO
2.3NoneExchange information about possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneInfo8
2.4NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.5NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.6NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.7NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.8NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.9NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.1NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.11NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
2.12NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.13NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.14NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.15NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.16NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.17NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.18NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.19NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.21NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
3.1NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO DSO
3.2NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO TSO
3.3NoneInforms the amount of flexibility requiredNoneNoneDSOMO DSOInfo11
3.4NoneInforms the amount of flexibility requiredNoneNoneTSOMO TSOInfo11
3.5NoneBids SelectionNoneNone
3.6NoneSelects the bids that may be a solutionFor DSONoneMO DSOMO DSO
3.7NoneSend the bidsFor DSONoneMO DSODSOInfo14
3.8NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For DSONoneDSODSO
3.9NoneSend the accepted/rejected bidsFor DSONoneDSOMO DSOInfo14
3.1NoneNotifies the resultFor DSONoneMO DSOFSP
3.11NoneSelects the bids that may be a solutionFor TSONoneMO TSOMO TSO
3.12NoneSend the bidsFor TSONoneMO TSOTSOInfo16
3.13NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For TSONoneTSOTSO
3.14NoneSend the accepted/rejected bidsFor TSONoneTSOMO TSOInfo16
3.15NoneCheck the Location of the bidsFor TSONoneMO TSOMO TSO
3.16NoneNotifies the resultFor TSO If the bid is connected to the Transmission GridNoneMO TSOFSP
3.17NoneSend the information of the bidFor TSO If the bid is connected to the Distribution GridNoneMO TSODSOInfo18
3.18NoneEvaluates grid constraintsFor TSO If the bid is connected to the Distribution GridNoneDSODSO
3.19NoneAccept/Reject bidFor TSO If the bid is connected to the Distribution GridNoneDSOMO TSOInfo19
3.2NoneNotifies the resultFor TSO If the bid is connected to the Distribution GridNoneMO TSOFSP
4.1NoneSharing of accepted bidsNoneNoneInfo20
4.2NoneChecks grid constrainsFor bids located in Distribution GridNoneDSODSO
4.3NoneInforms what Bids can/cannot be activatedFor bids located in Distribution GridNoneDSOTSOInfo20
4.4NoneChecks grid constrainsFor bids located in Transmission GridNoneTSOTSO
4.5NoneInforms what Bids can/cannot be activatedFor bids located in Transmission GridNoneTSODSOInfo20
4.6NoneAllows/Not allow bid activationNoneNoneDSOMO DSOInfo23
4.7NoneAllows/Not allow bid activationNoneNoneTSOMO TSOInfo24
4.8NoneInforms the resultNoneNoneMO DSOFSP
4.9NoneInforms the resultNoneNoneMO TSOFSP
4.1NoneInforms the activation of the bidNoneNoneFSPMO DSO
4.11NoneInforms the activation of the bidNoneNoneFSPMO TSO
Scenario Name:
Monitoring & Activation
Step No.Event.Name of Process/ ActivityDescription of Process/ Activity.ServiceInformation Producer (Actor)Information Receiver (Actor)Information ExchangedRequirements, R-ID
1.1FSP requests to be pre-qualifiedDefine the prequalification requirementsNoneNone
1.2NoneSend the prequalification requirementsNoneNoneDSOMO DSOInfo1
1.3NoneSend the prequalification requirementsNoneNoneTSOMO TSOInfo1
1.4NoneNotifies that he is interested in providing flexibility services.FOR DSONoneFSPMO DSO
1.5NoneSend the prequalification requirementsFOR DSONoneMO DSOFSPInfo1
1.6NoneForward the fulfilled prequalification requirementsFOR DSONoneFSPMO DSO
1.7NoneForward the fulfilled prequalification requirementsFOR DSONoneMO DSODSOInfo1
1.8NoneEvaluation of the Product & Grid prequalification requirementsFOR DSONoneDSODSO
1.9NoneRequest additional prequalification informationFOR DSONoneDSOMO DSO
1.1NoneRequest additional prequalification informationFOR DSONoneMO DSOFSP
1.11NoneSend additional prequalification informationFOR DSONoneFSPMO DSO
1.12NoneSend additional prequalification informationFOR DSONoneMO DSODSO
1.13NoneAccept / Reject registration on MarketFOR DSONoneDSOMO DSOInfo3
1.14NoneNotify of prequalification resultFOR DSONoneMO DSOFSP
1.15NoneNotifies that he is interested in providing flexibility services.FOR TSONoneFSPMO TSO
1.16NoneSend the prequalification requirementsFOR TSONoneMO TSOFSPInfo1
1.17NoneForward the fulfilled prequalification requirementsFOR TSONoneFSPMO TSO
1.18NoneChecks the Location of the FSPFOR TSONoneMO TSOMO TSO
1.19NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSOInfo1
1.2NoneEvaluation of the Product & Grid prequalification requirementsFOR TSO. If the FSP is connected to the Transmission GridNoneTSOTSO
1.21NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSO
1.22NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.23NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneFSPMO TSO
1.24NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOTSO
1.25NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Transmission GridNoneTSOMO TSOInfo5
1.26NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Transmission GridNoneMO TSOFSP
1.28NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSOInfo1
1.29NoneEvaluation of the Product prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOTSO
1.3NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSO
1.31NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.32NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.33NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOTSO
1.34NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneTSOMO TSOInfo5
1.35NoneForward the fulfilled prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSOInfo4
1.36NoneEvaluation of the Grid prequalification requirementsFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSODSO
1.37NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSO
1.38NoneRequest additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
1.39NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneFSPMO TSO
1.4NoneSend additional prequalification informationFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSODSO
1.41NoneAccept/Reject registration on MarketFOR TSO. If the FSP is connected to the Distribution Grid.NoneDSOMO TSOInfo7
1.42NoneNotify of prequalification resultFOR TSO. If the FSP is connected to the Distribution Grid.NoneMO TSOFSP
2.1NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOTSO
2.3NoneExchange information about possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneInfo8
2.4NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.5NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.6NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.7NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.8NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.9NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.1NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.11NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
2.12NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.13NoneMakes a forecast of possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSODSO
2.14NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneDSOMO DSOInfo8
2.15NoneInforms possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneTSOMO TSOInfo8
2.16NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO DSOFSP
2.17NonePublish the possible congestion areasDay-Ahead Market. Before Flexibility Market OpeningNoneMO TSOFSP
2.18NoneOptimize PortfolioDay-Ahead Market. Before Flexibility Market OpeningNoneFSPFSP
2.19NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneDSODSO
2.2NoneMakes a forecast of the grid status.
Check power flows.
Detect possible congestions
System reconfiguration
Assesses the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneTSOTSO
2.21NoneExchange information about the amount of flexibility requiredDay-Ahead Market. Flexibility Market OpeningNoneInfo11
3.1NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO DSO
3.2NoneOffer active power flexibility products.
Sends the baselines.NoneNoneFSPMO TSO
3.3NoneInforms the amount of flexibility requiredNoneNoneDSOMO DSOInfo11
3.4NoneInforms the amount of flexibility requiredNoneNoneTSOMO TSOInfo11
3.5NoneBids SelectionNoneNone
3.6NoneSelects the bids that may be a solutionFor DSONoneMO DSOMO DSO
3.7NoneSend the bidsFor DSONoneMO DSODSOInfo14
3.8NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For DSONoneDSODSO
3.9NoneSend the accepted/rejected bidsFor DSONoneDSOMO DSOInfo14
3.1NoneNotifies the resultFor DSONoneMO DSOFSP
3.11NoneSelects the bids that may be a solutionFor TSONoneMO TSOMO TSO
3.12NoneSend the bidsFor TSONoneMO TSOTSOInfo16
3.13NoneTechnical evaluation of the bids.
Accept bids.
Sort the bids by a merit order list.For TSONoneTSOTSO
3.14NoneSend the accepted/rejected bidsFor TSONoneTSOMO TSOInfo16
3.15NoneCheck the Location of the bidsFor TSONoneMO TSOMO TSO
3.16NoneNotifies the resultFor TSO If the bid is connected to the Transmission GridNoneMO TSOFSP
3.17NoneSend the information of the bidFor TSO If the bid is connected to the Distribution GridNoneMO TSODSOInfo18
3.18NoneEvaluates grid constraintsFor TSO If the bid is connected to the Distribution GridNoneDSODSO
3.19NoneAccept/Reject bidFor TSO If the bid is connected to the Distribution GridNoneDSOMO TSOInfo19
3.2NoneNotifies the resultFor TSO If the bid is connected to the Distribution GridNoneMO TSOFSP
4.1NoneSharing of accepted bidsNoneNoneInfo20
4.2NoneChecks grid constrainsFor bids located in Distribution GridNoneDSODSO
4.3NoneInforms what Bids can/cannot be activatedFor bids located in Distribution GridNoneDSOTSOInfo20
4.4NoneChecks grid constrainsFor bids located in Transmission GridNoneTSOTSO
4.5NoneInforms what Bids can/cannot be activatedFor bids located in Transmission GridNoneTSODSOInfo20
4.6NoneAllows/Not allow bid activationNoneNoneDSOMO DSOInfo23
4.7NoneAllows/Not allow bid activationNoneNoneTSOMO TSOInfo24
4.8NoneInforms the resultNoneNoneMO DSOFSP
4.9NoneInforms the resultNoneNoneMO TSOFSP
4.1NoneInforms the activation of the bidNoneNoneFSPMO DSO
4.11NoneInforms the activation of the bidNoneNoneFSPMO TSO

5. Information Exchanged

Information exchanged IDName of InformationDescription of Information ExchangedRequirement

6. Requirements (optional)

Category IdentifierNameDescriptionmRID
Req_IDReq_Name‘Exchange of Information for Congestion Management – Short Term’
IdentifierNameDescriptionmRID
Info1Prequalification requirements Mode of activation (If it is Automatic should be tested)
 Minimum Quantity (0.01 MW – 1 MW)
 Flexibility direction (load/generation reduction/increase, both)
 Locational information and SO connected
 Maximum duration of delivery period offer
 Single or Aggregated portfolio
 Capacity/Energy
 Maximum Full Activation time (60 minutes)Info1
Info2Fulfilled prequalification requirementsFor DSO. MO DSO -> DSOInfo1
Info3Accept / Reject registration on MarketFor DSO. DSO->MO DSOInfo3
Info4Fulfilled prequalification requirementsFor TSO. MO TSO->TSOInfo1
Info5Accept / Reject registration on MarketFor TSO. TSO->MO TSOInfo5
Info6Fulfilled prequalification requirementsFor TSO (in the Distribution Grid). MO TSO->DSOInfo4
Info7Accept / Reject registration on MarketFor TSO (in the Distribution Grid). DSO -> MO TSOInfo7
Info8Possible congestion areasDSO<->TSO. Grid areas where congestion may occurInfo8
Info9Possible congestion areasDSO->MO DSO. Grid areas where congestion may occurInfo8
Info10Possible congestion areasTSO->MO TSO. Grid areas where congestion may occurInfo8
Info11Amount of flexibility requiredDSO<->TSO. Flexibility quantity (MW)Info11
Info12Informs the amount of flexibility requiredDSO->MO DSO. Flexibility quantity (MW)Info11
Info13Informs the amount of flexibility requiredTSO->MO TSO. Flexibility quantity (MW)Info11
Info14Sends the bidsFor DSO. MO DSO->DSO. Characterization of the Bid (information, parameters, eg. Price, location, quantity)Info14
Info15Send the accepted/rejected bidsFor DSO. DSO-> MO DSO. Bid ID and result (accepted/rejected)Info14
Info16Sends the bidsFor TSO. MO TSO->TSO. For DSO. DSO-> MO DSO. Characterization of the Bid (information, parameters, eg. Price, location, quantity)Info16
Info17Send the accepted/rejected bidsFor TSO. TSO-> MO TSO. Bid ID and result (accepted/rejected)Info16
Info18Send the information of the bidFor TSO. TSO->MO DSO. For DSO. DSO-> MO DSO. Characterization of the Bid (information, parameters, eg, location, quantity)Info18
Info19Accept/Reject bidFor TSO. DSO->MO TSO. Bid ID and result (accepted/rejected)Info19
Info20Sharing of accepted bidsDSO<->TSO Characterization of the Bid (information, parameters, eg. Price, location, quantity)Info20
Info21Informs what Bids can/cannot be activatedDSO->TSO. Bid ID and result (accepted/rejected)Info20
Info22Informs what Bids can/cannot be activatedTSO->DSO. Bid ID and result (accepted/rejected)Info20
Info23Allows/Not allow bid activationDSO->MO DSO. Bid ID and result (accepted/rejected)Info23
Info24Allows/Not allow bid activationDSO->MO DSO. Bid ID and result (accepted/rejected)Info24

7. Common Terms and Definitions

8. Custom Information (optional)

KeyValueRefers to Section