ID | Area /Domain(s)/Zone(s) | Name of the Use Case |
---|---|---|
1 | None, | WECL-PT-01 |
Version No. | Date | Name of author(s) | Changes | Approval status |
---|---|---|---|---|
None | 2021-07-05T00:00:00 | E-REDES | ||
NESTER | ||||
REN | ||||
INESC TEC, | None | None |
Scope | This BUC is focused on describing in detail each process phase of the ASM report, stating what information should be exchanged and what rules should be established between DSO and TSO in order to procure congestion management products for short-term (intraday, day-ahead). |
Objective(s) | 1- Design and detail each process phase of ASM report so that it can serve as a basis for future developments. |
2- Coordination of the use of flexibility for different voltage levels. | |
3- Identify what information should be shared between DSO and TSO for each of the flexibility procurement process phases for short terms congestion management, namely for the technical selection and validation of the bids by the relevant system operator. | |
4- Develop information exchange mechanisms to enable market-based procurement of flexibility products. | |
Related business case(s) | WECL-PT-02, WECL-PT-03, SUC-01, SUC-02, SUC-03, SUC-04, SUC-05 |
Short description
Flexible resources connected to transmission and distribution system can provide flexibility to system operators to eliminate congestions through a market mechanism. This BUC in transmission and/or distribution system, in order to keep power flows within the accepted thermal limits of the lines. These information exchanges of information mechanisms should be adaptable to any future market model or governance issues. Some different time frame markets will be examined: • Day Ahead • Intraday For each time frame, we will approach some of the following process phases of ASM report:
Complete description
Flexible resources connected to transmission and distribution system can provide flexibility to system operators to eliminate congestions through a market mechanism. This BUC describes the exchanges of information and the processes that should be established for different scenarios: pre-qualification, plan/forecast, market phase and monitoring and activation phase. For each scenario, we will always take into account different timeframes (intraday and day-ahead) and how they are related. Pre-qualification The pre-qualification process should start after a flexibility service provider expresses interest in entering the flexibility market. This process serves to ensure that a particular flexibility service provider is capable of delivering a given product. In order to do that, two types of pre-qualification should be considered: Product Pre-qualification and Grid Pre-qualification. The former ensures that the resource contains the technical requirements to be able to deliver the product and proceed to the market phase and eventually selected by a system operator. These technical requirements are defined by DSO and TSO and after the FSP indicates the attributes of the product it wants to deliver, a pre-qualification test should be performed to verify that all attributes are in compliance with the technical requirements. This test may be repeated on a periodic basis or whenever the characteristics of the product are found to change significantly. The product pre-qualification can be done either by the DSO or TSO, regardless of its location. In case a system operator wants to activate a product already pre-qualified by another system operator, the former should have access to this information in order to make the process more efficient and not to pre-qualify the same product twice. Regarding grid pre-qualification, this process ensures that the product provided by the Flexible Service Provider will not cause constraints in the networks where it is connected. This process can be avoided if the System Operators have already identified the areas where flexibility is always allowed. The grid pre-qualification should be performed by the System Operator of the network to which the product is connected in order to verify if the maximum capacity of the product does not impact the network it is connected to. If the results of the two types of pre-qualification are approved, the entry of the FSP into the flexibility market is allowed. The Pre-qualification scenario is independent of the time-frame, since it is a process that happens before the market phase. Plan/Forecast In this phase the System Operators take into account the utilization of their grid. Based on forecasts the Systems Operators checks the power flows to detect whether or not there will be possible congestion in the network. In case the grid capacity is insufficient to meet the forecasted electricity production or consumption, System Operators may resort to the flexibility market to resolve this type of issue. This phase is done for two different timeframes, day-ahead and intraday. On the one hand, the day-ahead forecasts are made for D-1. On the other hand, the intraday forecasts are made every 4 hours in order to improve the accuracy of the predicted flow of electricity that were made for the day-ahead. The objectives of this phase are to identify possible congestions in the network and to support the procurement in the flexibility markets. Market Phase The market phase starts after the system operators forecast network congestion. In this phase, the system operators are focused on collecting and selecting bids from FSPs. These bids can be in the day-ahead market, which occurs on D-1, in the intraday market, which occurs already inside D every 4 hours, or they can come from the long-term market (BUC-2). The intraday market is a complement to the day-ahead market. The possible failures or unforeseen events that were not covered in the day-ahead should be corrected in the intraday market. In the bid selection process, the SO should pay attention to whether the bid is located in its own network, or in another network. In the latter case, the SO should consult the SO where the bid is located so it can evaluate the constraints that may arise if the bid is accepted and activated. After this phase, the need arises to sort the accepted bids by a merit order list. This Business Use Case will address a multi-level market model. Monitoring and Activation This phase occurs after the list of bids sorted by a merit order is defined. The SO selects the bid it wants to activate, if the bid is located in the network of another SO, the latter should be consulted to validate the activation of this bid. If the SO’s need is not resolved this process is repeated iteratively until the SO needs are solved.
ID | Name | Description | Reference to mentioned use case objectives |
---|
Assumptions |
---|
WECL-PT-01 |
Prerequisites |
---|
WECL-PT-01 |
Relation to other use cases |
---|
Level of depth |
Prioritisation |
Generic, regional or national relation |
Generic |
Nature of the use cases |
Business Use Case |
Further keywords for classification |
Congestion management, DSO-TSO Coordination, DSO-TSO Exchange of Information |
General remarks |
---|
Actor Name | Actor Type | Actor Description | Further information specific to this Use Case |
---|---|---|---|
DSO | Role | According to the EDSO, the DSOs are “the operating managers (and sometimes owners) of energy distribution networks, operating at low, medium and, in some member states, high voltage levels (LV, MV)”. | |
TSO | Role | According to the European Commission, the TSO is “an organisation committed to transporting energy in the form of natural gas or electrical power on a national or regional level, using fixed infrastructure”. The certification procedure for TSOs is listed in Article 10 of the 2009 Electricity and Gas Directives. | |
MO DSO | Role | According to Article 2(7) of the Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast), market operator designates “an entity that provides a service whereby the offers to sell electricity are matched with bids to buy electricity”. | |
MO TSO | Role | According to Article 2(7) of the Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast), market operator designates “an entity that provides a service whereby the offers to sell electricity are matched with bids to buy electricity”. | |
FSP | Role | Defined as any legal entity that offers flexibility services in the market. |
No. | References Type | Reference | Status | Impact on Use Case | Organistaor / Organisation | Link |
---|
No. | Scenario Name | Scenario Description | Primary Actor | Triggering Event | Pre-Condition | Post-Condition |
---|---|---|---|---|---|---|
None | Prepare/Prequalification | The process in which it is checked whether a unit can deliver the product it intends to sell, taking into account the network conditions | Prepare/Prequalification | |||
None | Plan/Forecast | Planning of grid utilization and identifying potential congestions. | Plan/Forecast | |||
None | Market Phase | Bids collection and selection, short-term contracts (capacity products) and short-term products/services (selection of energy products). | Market Phase | |||
None | Monitoring & Activation | Grid monitoring and flexibility bids activation to solve the forecasted congestion management. | Monitoring & Activation |
Notes
Scenario Name: |
---|
Prepare/Prequalification |
Step No. | Event. | Name of Process/ Activity | Description of Process/ Activity. | Service | Information Producer (Actor) | Information Receiver (Actor) | Information Exchanged | Requirements, R-ID |
---|---|---|---|---|---|---|---|---|
1.1 | FSP requests to be pre-qualified | Define the prequalification requirements | None | None | ||||
1.2 | None | Send the prequalification requirements | None | None | DSO | MO DSO | Info1 | |
1.3 | None | Send the prequalification requirements | None | None | TSO | MO TSO | Info1 | |
1.4 | None | Notifies that he is interested in providing flexibility services. | FOR DSO | None | FSP | MO DSO | ||
1.5 | None | Send the prequalification requirements | FOR DSO | None | MO DSO | FSP | Info1 | |
1.6 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | FSP | MO DSO | ||
1.7 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | MO DSO | DSO | Info1 | |
1.8 | None | Evaluation of the Product & Grid prequalification requirements | FOR DSO | None | DSO | DSO | ||
1.9 | None | Request additional prequalification information | FOR DSO | None | DSO | MO DSO | ||
1.1 | None | Request additional prequalification information | FOR DSO | None | MO DSO | FSP | ||
1.11 | None | Send additional prequalification information | FOR DSO | None | FSP | MO DSO | ||
1.12 | None | Send additional prequalification information | FOR DSO | None | MO DSO | DSO | ||
1.13 | None | Accept / Reject registration on Market | FOR DSO | None | DSO | MO DSO | Info3 | |
1.14 | None | Notify of prequalification result | FOR DSO | None | MO DSO | FSP | ||
1.15 | None | Notifies that he is interested in providing flexibility services. | FOR TSO | None | FSP | MO TSO | ||
1.16 | None | Send the prequalification requirements | FOR TSO | None | MO TSO | FSP | Info1 | |
1.17 | None | Forward the fulfilled prequalification requirements | FOR TSO | None | FSP | MO TSO | ||
1.18 | None | Checks the Location of the FSP | FOR TSO | None | MO TSO | MO TSO | ||
1.19 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | Info1 | |
1.2 | None | Evaluation of the Product & Grid prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | TSO | ||
1.21 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | ||
1.22 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.23 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | FSP | MO TSO | ||
1.24 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | ||
1.25 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | Info5 | |
1.26 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.28 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | Info1 | |
1.29 | None | Evaluation of the Product prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | TSO | ||
1.3 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | ||
1.31 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.32 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.33 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | ||
1.34 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | Info5 | |
1.35 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | Info4 | |
1.36 | None | Evaluation of the Grid prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | DSO | ||
1.37 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | ||
1.38 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.39 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.4 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | ||
1.41 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | Info7 | |
1.42 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
2.1 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.2 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | TSO | ||
2.3 | None | Exchange information about possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | Info8 | |||
2.4 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.5 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.6 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.7 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.8 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.9 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.1 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.11 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
2.12 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.13 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.14 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.15 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.16 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.17 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.18 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.19 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.2 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.21 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
3.1 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO DSO | ||||
3.2 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO TSO | ||||
3.3 | None | Informs the amount of flexibility required | None | None | DSO | MO DSO | Info11 | |
3.4 | None | Informs the amount of flexibility required | None | None | TSO | MO TSO | Info11 | |
3.5 | None | Bids Selection | None | None | ||||
3.6 | None | Selects the bids that may be a solution | For DSO | None | MO DSO | MO DSO | ||
3.7 | None | Send the bids | For DSO | None | MO DSO | DSO | Info14 | |
3.8 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For DSO | None | DSO | DSO | ||||
3.9 | None | Send the accepted/rejected bids | For DSO | None | DSO | MO DSO | Info14 | |
3.1 | None | Notifies the result | For DSO | None | MO DSO | FSP | ||
3.11 | None | Selects the bids that may be a solution | For TSO | None | MO TSO | MO TSO | ||
3.12 | None | Send the bids | For TSO | None | MO TSO | TSO | Info16 | |
3.13 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For TSO | None | TSO | TSO | ||||
3.14 | None | Send the accepted/rejected bids | For TSO | None | TSO | MO TSO | Info16 | |
3.15 | None | Check the Location of the bids | For TSO | None | MO TSO | MO TSO | ||
3.16 | None | Notifies the result | For TSO If the bid is connected to the Transmission Grid | None | MO TSO | FSP | ||
3.17 | None | Send the information of the bid | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | DSO | Info18 | |
3.18 | None | Evaluates grid constraints | For TSO If the bid is connected to the Distribution Grid | None | DSO | DSO | ||
3.19 | None | Accept/Reject bid | For TSO If the bid is connected to the Distribution Grid | None | DSO | MO TSO | Info19 | |
3.2 | None | Notifies the result | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | FSP | ||
4.1 | None | Sharing of accepted bids | None | None | Info20 | |||
4.2 | None | Checks grid constrains | For bids located in Distribution Grid | None | DSO | DSO | ||
4.3 | None | Informs what Bids can/cannot be activated | For bids located in Distribution Grid | None | DSO | TSO | Info20 | |
4.4 | None | Checks grid constrains | For bids located in Transmission Grid | None | TSO | TSO | ||
4.5 | None | Informs what Bids can/cannot be activated | For bids located in Transmission Grid | None | TSO | DSO | Info20 | |
4.6 | None | Allows/Not allow bid activation | None | None | DSO | MO DSO | Info23 | |
4.7 | None | Allows/Not allow bid activation | None | None | TSO | MO TSO | Info24 | |
4.8 | None | Informs the result | None | None | MO DSO | FSP | ||
4.9 | None | Informs the result | None | None | MO TSO | FSP | ||
4.1 | None | Informs the activation of the bid | None | None | FSP | MO DSO | ||
4.11 | None | Informs the activation of the bid | None | None | FSP | MO TSO |
Scenario Name: |
---|
Plan/Forecast |
Step No. | Event. | Name of Process/ Activity | Description of Process/ Activity. | Service | Information Producer (Actor) | Information Receiver (Actor) | Information Exchanged | Requirements, R-ID |
---|---|---|---|---|---|---|---|---|
1.1 | FSP requests to be pre-qualified | Define the prequalification requirements | None | None | ||||
1.2 | None | Send the prequalification requirements | None | None | DSO | MO DSO | Info1 | |
1.3 | None | Send the prequalification requirements | None | None | TSO | MO TSO | Info1 | |
1.4 | None | Notifies that he is interested in providing flexibility services. | FOR DSO | None | FSP | MO DSO | ||
1.5 | None | Send the prequalification requirements | FOR DSO | None | MO DSO | FSP | Info1 | |
1.6 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | FSP | MO DSO | ||
1.7 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | MO DSO | DSO | Info1 | |
1.8 | None | Evaluation of the Product & Grid prequalification requirements | FOR DSO | None | DSO | DSO | ||
1.9 | None | Request additional prequalification information | FOR DSO | None | DSO | MO DSO | ||
1.1 | None | Request additional prequalification information | FOR DSO | None | MO DSO | FSP | ||
1.11 | None | Send additional prequalification information | FOR DSO | None | FSP | MO DSO | ||
1.12 | None | Send additional prequalification information | FOR DSO | None | MO DSO | DSO | ||
1.13 | None | Accept / Reject registration on Market | FOR DSO | None | DSO | MO DSO | Info3 | |
1.14 | None | Notify of prequalification result | FOR DSO | None | MO DSO | FSP | ||
1.15 | None | Notifies that he is interested in providing flexibility services. | FOR TSO | None | FSP | MO TSO | ||
1.16 | None | Send the prequalification requirements | FOR TSO | None | MO TSO | FSP | Info1 | |
1.17 | None | Forward the fulfilled prequalification requirements | FOR TSO | None | FSP | MO TSO | ||
1.18 | None | Checks the Location of the FSP | FOR TSO | None | MO TSO | MO TSO | ||
1.19 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | Info1 | |
1.2 | None | Evaluation of the Product & Grid prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | TSO | ||
1.21 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | ||
1.22 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.23 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | FSP | MO TSO | ||
1.24 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | ||
1.25 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | Info5 | |
1.26 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.28 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | Info1 | |
1.29 | None | Evaluation of the Product prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | TSO | ||
1.3 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | ||
1.31 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.32 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.33 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | ||
1.34 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | Info5 | |
1.35 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | Info4 | |
1.36 | None | Evaluation of the Grid prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | DSO | ||
1.37 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | ||
1.38 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.39 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.4 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | ||
1.41 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | Info7 | |
1.42 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
2.1 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.2 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | TSO | ||
2.3 | None | Exchange information about possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | Info8 | |||
2.4 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.5 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.6 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.7 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.8 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.9 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.1 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.11 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
2.12 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.13 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.14 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.15 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.16 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.17 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.18 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.19 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.2 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.21 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
3.1 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO DSO | ||||
3.2 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO TSO | ||||
3.3 | None | Informs the amount of flexibility required | None | None | DSO | MO DSO | Info11 | |
3.4 | None | Informs the amount of flexibility required | None | None | TSO | MO TSO | Info11 | |
3.5 | None | Bids Selection | None | None | ||||
3.6 | None | Selects the bids that may be a solution | For DSO | None | MO DSO | MO DSO | ||
3.7 | None | Send the bids | For DSO | None | MO DSO | DSO | Info14 | |
3.8 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For DSO | None | DSO | DSO | ||||
3.9 | None | Send the accepted/rejected bids | For DSO | None | DSO | MO DSO | Info14 | |
3.1 | None | Notifies the result | For DSO | None | MO DSO | FSP | ||
3.11 | None | Selects the bids that may be a solution | For TSO | None | MO TSO | MO TSO | ||
3.12 | None | Send the bids | For TSO | None | MO TSO | TSO | Info16 | |
3.13 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For TSO | None | TSO | TSO | ||||
3.14 | None | Send the accepted/rejected bids | For TSO | None | TSO | MO TSO | Info16 | |
3.15 | None | Check the Location of the bids | For TSO | None | MO TSO | MO TSO | ||
3.16 | None | Notifies the result | For TSO If the bid is connected to the Transmission Grid | None | MO TSO | FSP | ||
3.17 | None | Send the information of the bid | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | DSO | Info18 | |
3.18 | None | Evaluates grid constraints | For TSO If the bid is connected to the Distribution Grid | None | DSO | DSO | ||
3.19 | None | Accept/Reject bid | For TSO If the bid is connected to the Distribution Grid | None | DSO | MO TSO | Info19 | |
3.2 | None | Notifies the result | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | FSP | ||
4.1 | None | Sharing of accepted bids | None | None | Info20 | |||
4.2 | None | Checks grid constrains | For bids located in Distribution Grid | None | DSO | DSO | ||
4.3 | None | Informs what Bids can/cannot be activated | For bids located in Distribution Grid | None | DSO | TSO | Info20 | |
4.4 | None | Checks grid constrains | For bids located in Transmission Grid | None | TSO | TSO | ||
4.5 | None | Informs what Bids can/cannot be activated | For bids located in Transmission Grid | None | TSO | DSO | Info20 | |
4.6 | None | Allows/Not allow bid activation | None | None | DSO | MO DSO | Info23 | |
4.7 | None | Allows/Not allow bid activation | None | None | TSO | MO TSO | Info24 | |
4.8 | None | Informs the result | None | None | MO DSO | FSP | ||
4.9 | None | Informs the result | None | None | MO TSO | FSP | ||
4.1 | None | Informs the activation of the bid | None | None | FSP | MO DSO | ||
4.11 | None | Informs the activation of the bid | None | None | FSP | MO TSO |
Scenario Name: |
---|
Market Phase |
Step No. | Event. | Name of Process/ Activity | Description of Process/ Activity. | Service | Information Producer (Actor) | Information Receiver (Actor) | Information Exchanged | Requirements, R-ID |
---|---|---|---|---|---|---|---|---|
1.1 | FSP requests to be pre-qualified | Define the prequalification requirements | None | None | ||||
1.2 | None | Send the prequalification requirements | None | None | DSO | MO DSO | Info1 | |
1.3 | None | Send the prequalification requirements | None | None | TSO | MO TSO | Info1 | |
1.4 | None | Notifies that he is interested in providing flexibility services. | FOR DSO | None | FSP | MO DSO | ||
1.5 | None | Send the prequalification requirements | FOR DSO | None | MO DSO | FSP | Info1 | |
1.6 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | FSP | MO DSO | ||
1.7 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | MO DSO | DSO | Info1 | |
1.8 | None | Evaluation of the Product & Grid prequalification requirements | FOR DSO | None | DSO | DSO | ||
1.9 | None | Request additional prequalification information | FOR DSO | None | DSO | MO DSO | ||
1.1 | None | Request additional prequalification information | FOR DSO | None | MO DSO | FSP | ||
1.11 | None | Send additional prequalification information | FOR DSO | None | FSP | MO DSO | ||
1.12 | None | Send additional prequalification information | FOR DSO | None | MO DSO | DSO | ||
1.13 | None | Accept / Reject registration on Market | FOR DSO | None | DSO | MO DSO | Info3 | |
1.14 | None | Notify of prequalification result | FOR DSO | None | MO DSO | FSP | ||
1.15 | None | Notifies that he is interested in providing flexibility services. | FOR TSO | None | FSP | MO TSO | ||
1.16 | None | Send the prequalification requirements | FOR TSO | None | MO TSO | FSP | Info1 | |
1.17 | None | Forward the fulfilled prequalification requirements | FOR TSO | None | FSP | MO TSO | ||
1.18 | None | Checks the Location of the FSP | FOR TSO | None | MO TSO | MO TSO | ||
1.19 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | Info1 | |
1.2 | None | Evaluation of the Product & Grid prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | TSO | ||
1.21 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | ||
1.22 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.23 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | FSP | MO TSO | ||
1.24 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | ||
1.25 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | Info5 | |
1.26 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.28 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | Info1 | |
1.29 | None | Evaluation of the Product prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | TSO | ||
1.3 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | ||
1.31 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.32 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.33 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | ||
1.34 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | Info5 | |
1.35 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | Info4 | |
1.36 | None | Evaluation of the Grid prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | DSO | ||
1.37 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | ||
1.38 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.39 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.4 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | ||
1.41 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | Info7 | |
1.42 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
2.1 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.2 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | TSO | ||
2.3 | None | Exchange information about possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | Info8 | |||
2.4 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.5 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.6 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.7 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.8 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.9 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.1 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.11 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
2.12 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.13 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.14 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.15 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.16 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.17 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.18 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.19 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.2 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.21 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
3.1 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO DSO | ||||
3.2 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO TSO | ||||
3.3 | None | Informs the amount of flexibility required | None | None | DSO | MO DSO | Info11 | |
3.4 | None | Informs the amount of flexibility required | None | None | TSO | MO TSO | Info11 | |
3.5 | None | Bids Selection | None | None | ||||
3.6 | None | Selects the bids that may be a solution | For DSO | None | MO DSO | MO DSO | ||
3.7 | None | Send the bids | For DSO | None | MO DSO | DSO | Info14 | |
3.8 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For DSO | None | DSO | DSO | ||||
3.9 | None | Send the accepted/rejected bids | For DSO | None | DSO | MO DSO | Info14 | |
3.1 | None | Notifies the result | For DSO | None | MO DSO | FSP | ||
3.11 | None | Selects the bids that may be a solution | For TSO | None | MO TSO | MO TSO | ||
3.12 | None | Send the bids | For TSO | None | MO TSO | TSO | Info16 | |
3.13 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For TSO | None | TSO | TSO | ||||
3.14 | None | Send the accepted/rejected bids | For TSO | None | TSO | MO TSO | Info16 | |
3.15 | None | Check the Location of the bids | For TSO | None | MO TSO | MO TSO | ||
3.16 | None | Notifies the result | For TSO If the bid is connected to the Transmission Grid | None | MO TSO | FSP | ||
3.17 | None | Send the information of the bid | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | DSO | Info18 | |
3.18 | None | Evaluates grid constraints | For TSO If the bid is connected to the Distribution Grid | None | DSO | DSO | ||
3.19 | None | Accept/Reject bid | For TSO If the bid is connected to the Distribution Grid | None | DSO | MO TSO | Info19 | |
3.2 | None | Notifies the result | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | FSP | ||
4.1 | None | Sharing of accepted bids | None | None | Info20 | |||
4.2 | None | Checks grid constrains | For bids located in Distribution Grid | None | DSO | DSO | ||
4.3 | None | Informs what Bids can/cannot be activated | For bids located in Distribution Grid | None | DSO | TSO | Info20 | |
4.4 | None | Checks grid constrains | For bids located in Transmission Grid | None | TSO | TSO | ||
4.5 | None | Informs what Bids can/cannot be activated | For bids located in Transmission Grid | None | TSO | DSO | Info20 | |
4.6 | None | Allows/Not allow bid activation | None | None | DSO | MO DSO | Info23 | |
4.7 | None | Allows/Not allow bid activation | None | None | TSO | MO TSO | Info24 | |
4.8 | None | Informs the result | None | None | MO DSO | FSP | ||
4.9 | None | Informs the result | None | None | MO TSO | FSP | ||
4.1 | None | Informs the activation of the bid | None | None | FSP | MO DSO | ||
4.11 | None | Informs the activation of the bid | None | None | FSP | MO TSO |
Scenario Name: |
---|
Monitoring & Activation |
Step No. | Event. | Name of Process/ Activity | Description of Process/ Activity. | Service | Information Producer (Actor) | Information Receiver (Actor) | Information Exchanged | Requirements, R-ID |
---|---|---|---|---|---|---|---|---|
1.1 | FSP requests to be pre-qualified | Define the prequalification requirements | None | None | ||||
1.2 | None | Send the prequalification requirements | None | None | DSO | MO DSO | Info1 | |
1.3 | None | Send the prequalification requirements | None | None | TSO | MO TSO | Info1 | |
1.4 | None | Notifies that he is interested in providing flexibility services. | FOR DSO | None | FSP | MO DSO | ||
1.5 | None | Send the prequalification requirements | FOR DSO | None | MO DSO | FSP | Info1 | |
1.6 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | FSP | MO DSO | ||
1.7 | None | Forward the fulfilled prequalification requirements | FOR DSO | None | MO DSO | DSO | Info1 | |
1.8 | None | Evaluation of the Product & Grid prequalification requirements | FOR DSO | None | DSO | DSO | ||
1.9 | None | Request additional prequalification information | FOR DSO | None | DSO | MO DSO | ||
1.1 | None | Request additional prequalification information | FOR DSO | None | MO DSO | FSP | ||
1.11 | None | Send additional prequalification information | FOR DSO | None | FSP | MO DSO | ||
1.12 | None | Send additional prequalification information | FOR DSO | None | MO DSO | DSO | ||
1.13 | None | Accept / Reject registration on Market | FOR DSO | None | DSO | MO DSO | Info3 | |
1.14 | None | Notify of prequalification result | FOR DSO | None | MO DSO | FSP | ||
1.15 | None | Notifies that he is interested in providing flexibility services. | FOR TSO | None | FSP | MO TSO | ||
1.16 | None | Send the prequalification requirements | FOR TSO | None | MO TSO | FSP | Info1 | |
1.17 | None | Forward the fulfilled prequalification requirements | FOR TSO | None | FSP | MO TSO | ||
1.18 | None | Checks the Location of the FSP | FOR TSO | None | MO TSO | MO TSO | ||
1.19 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | Info1 | |
1.2 | None | Evaluation of the Product & Grid prequalification requirements | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | TSO | ||
1.21 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | ||
1.22 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.23 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | FSP | MO TSO | ||
1.24 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | TSO | ||
1.25 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Transmission Grid | None | TSO | MO TSO | Info5 | |
1.26 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Transmission Grid | None | MO TSO | FSP | ||
1.28 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | Info1 | |
1.29 | None | Evaluation of the Product prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | TSO | ||
1.3 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | ||
1.31 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.32 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.33 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | TSO | ||
1.34 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | TSO | MO TSO | Info5 | |
1.35 | None | Forward the fulfilled prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | Info4 | |
1.36 | None | Evaluation of the Grid prequalification requirements | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | DSO | ||
1.37 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | ||
1.38 | None | Request additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
1.39 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | FSP | MO TSO | ||
1.4 | None | Send additional prequalification information | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | DSO | ||
1.41 | None | Accept/Reject registration on Market | FOR TSO. If the FSP is connected to the Distribution Grid. | None | DSO | MO TSO | Info7 | |
1.42 | None | Notify of prequalification result | FOR TSO. If the FSP is connected to the Distribution Grid. | None | MO TSO | FSP | ||
2.1 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.2 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | TSO | ||
2.3 | None | Exchange information about possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | Info8 | |||
2.4 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.5 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.6 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.7 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.8 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.9 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.1 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.11 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
2.12 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.13 | None | Makes a forecast of possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | DSO | ||
2.14 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | DSO | MO DSO | Info8 | |
2.15 | None | Informs possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | TSO | MO TSO | Info8 | |
2.16 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO DSO | FSP | ||
2.17 | None | Publish the possible congestion areas | Day-Ahead Market. Before Flexibility Market Opening | None | MO TSO | FSP | ||
2.18 | None | Optimize Portfolio | Day-Ahead Market. Before Flexibility Market Opening | None | FSP | FSP | ||
2.19 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | DSO | DSO | ||||
2.2 | None | Makes a forecast of the grid status. | ||||||
Check power flows. | ||||||||
Detect possible congestions | ||||||||
System reconfiguration | ||||||||
Assesses the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | TSO | TSO | ||||
2.21 | None | Exchange information about the amount of flexibility required | Day-Ahead Market. Flexibility Market Opening | None | Info11 | |||
3.1 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO DSO | ||||
3.2 | None | Offer active power flexibility products. | ||||||
Sends the baselines. | None | None | FSP | MO TSO | ||||
3.3 | None | Informs the amount of flexibility required | None | None | DSO | MO DSO | Info11 | |
3.4 | None | Informs the amount of flexibility required | None | None | TSO | MO TSO | Info11 | |
3.5 | None | Bids Selection | None | None | ||||
3.6 | None | Selects the bids that may be a solution | For DSO | None | MO DSO | MO DSO | ||
3.7 | None | Send the bids | For DSO | None | MO DSO | DSO | Info14 | |
3.8 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For DSO | None | DSO | DSO | ||||
3.9 | None | Send the accepted/rejected bids | For DSO | None | DSO | MO DSO | Info14 | |
3.1 | None | Notifies the result | For DSO | None | MO DSO | FSP | ||
3.11 | None | Selects the bids that may be a solution | For TSO | None | MO TSO | MO TSO | ||
3.12 | None | Send the bids | For TSO | None | MO TSO | TSO | Info16 | |
3.13 | None | Technical evaluation of the bids. | ||||||
Accept bids. | ||||||||
Sort the bids by a merit order list. | For TSO | None | TSO | TSO | ||||
3.14 | None | Send the accepted/rejected bids | For TSO | None | TSO | MO TSO | Info16 | |
3.15 | None | Check the Location of the bids | For TSO | None | MO TSO | MO TSO | ||
3.16 | None | Notifies the result | For TSO If the bid is connected to the Transmission Grid | None | MO TSO | FSP | ||
3.17 | None | Send the information of the bid | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | DSO | Info18 | |
3.18 | None | Evaluates grid constraints | For TSO If the bid is connected to the Distribution Grid | None | DSO | DSO | ||
3.19 | None | Accept/Reject bid | For TSO If the bid is connected to the Distribution Grid | None | DSO | MO TSO | Info19 | |
3.2 | None | Notifies the result | For TSO If the bid is connected to the Distribution Grid | None | MO TSO | FSP | ||
4.1 | None | Sharing of accepted bids | None | None | Info20 | |||
4.2 | None | Checks grid constrains | For bids located in Distribution Grid | None | DSO | DSO | ||
4.3 | None | Informs what Bids can/cannot be activated | For bids located in Distribution Grid | None | DSO | TSO | Info20 | |
4.4 | None | Checks grid constrains | For bids located in Transmission Grid | None | TSO | TSO | ||
4.5 | None | Informs what Bids can/cannot be activated | For bids located in Transmission Grid | None | TSO | DSO | Info20 | |
4.6 | None | Allows/Not allow bid activation | None | None | DSO | MO DSO | Info23 | |
4.7 | None | Allows/Not allow bid activation | None | None | TSO | MO TSO | Info24 | |
4.8 | None | Informs the result | None | None | MO DSO | FSP | ||
4.9 | None | Informs the result | None | None | MO TSO | FSP | ||
4.1 | None | Informs the activation of the bid | None | None | FSP | MO DSO | ||
4.11 | None | Informs the activation of the bid | None | None | FSP | MO TSO |
Information exchanged ID | Name of Information | Description of Information Exchanged | Requirement |
---|
Category Identifier | Name | Description | mRID |
---|---|---|---|
Req_ID | Req_Name | ‘Exchange of Information for Congestion Management – Short Term’ |
Identifier | Name | Description | mRID |
---|---|---|---|
Info1 | Prequalification requirements | Mode of activation (If it is Automatic should be tested) | |
Minimum Quantity (0.01 MW – 1 MW) | |||
Flexibility direction (load/generation reduction/increase, both) | |||
Locational information and SO connected | |||
Maximum duration of delivery period offer | |||
Single or Aggregated portfolio | |||
Capacity/Energy | |||
Maximum Full Activation time (60 minutes) | Info1 | ||
Info2 | Fulfilled prequalification requirements | For DSO. MO DSO -> DSO | Info1 |
Info3 | Accept / Reject registration on Market | For DSO. DSO->MO DSO | Info3 |
Info4 | Fulfilled prequalification requirements | For TSO. MO TSO->TSO | Info1 |
Info5 | Accept / Reject registration on Market | For TSO. TSO->MO TSO | Info5 |
Info6 | Fulfilled prequalification requirements | For TSO (in the Distribution Grid). MO TSO->DSO | Info4 |
Info7 | Accept / Reject registration on Market | For TSO (in the Distribution Grid). DSO -> MO TSO | Info7 |
Info8 | Possible congestion areas | DSO<->TSO. Grid areas where congestion may occur | Info8 |
Info9 | Possible congestion areas | DSO->MO DSO. Grid areas where congestion may occur | Info8 |
Info10 | Possible congestion areas | TSO->MO TSO. Grid areas where congestion may occur | Info8 |
Info11 | Amount of flexibility required | DSO<->TSO. Flexibility quantity (MW) | Info11 |
Info12 | Informs the amount of flexibility required | DSO->MO DSO. Flexibility quantity (MW) | Info11 |
Info13 | Informs the amount of flexibility required | TSO->MO TSO. Flexibility quantity (MW) | Info11 |
Info14 | Sends the bids | For DSO. MO DSO->DSO. Characterization of the Bid (information, parameters, eg. Price, location, quantity) | Info14 |
Info15 | Send the accepted/rejected bids | For DSO. DSO-> MO DSO. Bid ID and result (accepted/rejected) | Info14 |
Info16 | Sends the bids | For TSO. MO TSO->TSO. For DSO. DSO-> MO DSO. Characterization of the Bid (information, parameters, eg. Price, location, quantity) | Info16 |
Info17 | Send the accepted/rejected bids | For TSO. TSO-> MO TSO. Bid ID and result (accepted/rejected) | Info16 |
Info18 | Send the information of the bid | For TSO. TSO->MO DSO. For DSO. DSO-> MO DSO. Characterization of the Bid (information, parameters, eg, location, quantity) | Info18 |
Info19 | Accept/Reject bid | For TSO. DSO->MO TSO. Bid ID and result (accepted/rejected) | Info19 |
Info20 | Sharing of accepted bids | DSO<->TSO Characterization of the Bid (information, parameters, eg. Price, location, quantity) | Info20 |
Info21 | Informs what Bids can/cannot be activated | DSO->TSO. Bid ID and result (accepted/rejected) | Info20 |
Info22 | Informs what Bids can/cannot be activated | TSO->DSO. Bid ID and result (accepted/rejected) | Info20 |
Info23 | Allows/Not allow bid activation | DSO->MO DSO. Bid ID and result (accepted/rejected) | Info23 |
Info24 | Allows/Not allow bid activation | DSO->MO DSO. Bid ID and result (accepted/rejected) | Info24 |
Key | Value | Refers to Section |
---|